Bacton Gas Terminal

Date: 
August 2016 to September 2016

Work involved: This project involved the supply of our positive pressure Habitat again for Shell to use on their gas refinery plant in Bacton. The use of the habitat on site allowed for remedial welding work to take place iside the vessel of the boiler. Both ends of the vessel had to be sealed and pressurised, therefore we had a space of over 100m3 to pressurise and monitor. Due to the speed of construction of our habitat and the pre-calibration of all of our equipment, we completed the project 1 day ahead of schedule.